Objectives
- Specification of interfaces and provision of a control and timing system to allow multiple detectors to be linked together.
- Develop a central data acquisition software and run control to enable multiple detectors to be combined in one experiment.
- Develop monitoring systems to automatically check the data quality.
- Develop a system to monitor the environmental conditions, such as temperature, of several detectors.
- Define an event for online data where data is combined from detectors with very different signals and properties.
For ongoing work, see the group's work page.
Tasks
Task | Task leaders |
---|---|
Task 5.1 Scientific coordination | David Cussans (UNIBRIS) Matthew Wing (UCL) |
Task 5.2 Interface, synchronisation and control of multiple-detector systems | David Cussans (UNIBRIS) |
Task 5.3 Development of central DAQ software and run control | Matthew Wing (UCL) |
Task 5.4 Development of data quality and slow control monitoring | Fabrizio Salvatore (USSUS) |
Task 5.5 Event model for combined DAQ | Adrian Irles (DESY) |
WP5 Technology Transfer Officer | Matthew Wing (UCL) |
Deliverables
Del. no. | Deliverable name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
D5.1 | Interface definition | 5 | M15 | 05/09/2016 | Achieved | Report |
D5.2 | Trigger Logic Unit ready | 5 | M30 | 15/12/2017 | Achieved | Report |
D5.3 | Data acquisition software | 5 | M30 | 06/12/2017 | Achieved | Report |
D5.4 | Data acquisition hardware | 5 | M30 | 22/12/2017 | Achieved | Report |
D5.5 | Online event data model | 5 | M30 | 30/11/2017 | Achieved | Report |
D5.6 | Common DAQ system used in combined beam tests | 5 | M57 | 31/01/2020 | Achieved | Report |
Milestones
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
MS25 | Definition of detector interface standards with common DAQ | 5 | M15 | 15/08/2016 | Achieved | Report |
MS43 | Trigger logic unit (TLU) design ready | 5 | M21 | 06/02/2017 | Achieved | Report |
MS46 | EUDAQ interfaces to other DAQs available | 5 | M24 | 23/06/2017 | Achieved | Report |
MS47 | Online event data model available | 5 | M24 | 09/06/2017 | Achieved | Report |
MS62 | Development of run control ready | 5 | M27 | 31/07/2017 | Achieved | Report |
MS66 | TLU hardware, firmware and software ready for tests beams | 5 | M30 | 30/11/2017 | Achieved | Report |
MS67 | Data quality monitoring tools ready | 5 | M30 | 06/11/2017 | Achieved | Report |
MS68 | Slow control system ready | 5 | M30 | 18/12/2017 | Achieved | Report |
MS80 | Common DAQ system ready for combined test beams | 5 | M36 | 19/04/2018 | Achieved | Report |
Publications
The list of WP5 publications can be found in CDS.