Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS1 | Consortium Agreement signed | 1 | M1 | 05/06/2015 | Achieved | |
MS2 | Project Website launched | 2 | M1 | 03/06/2015 | Achieved | Report |
MS3 | AIDA-2020 Kick-off meeting | 1 | M2 | 22/06/2015 | Achieved | Report |
MS4 | Project Communication Plan | 2 | M2 | 30/06/2015 | Achieved | Report |
MS5 | Network of Technology Transfer Officers established | 2 | M3 | 27/07/2015 | Achieved | Report |
MS6 | Non-disclosure Agreement and Background declarations ready | 2 | M3 | 05/06/2015 | Achieved | Part of the CA |
MS7 | Simulation workshop on HV/HR-CMOS TCAD and Geant4 simulations | 6 | M6 | 26/05/2016 | Achieved | |
MS8 | Advanced Mechanical Distributed facility requirements | 9 | M9 | 16/06/2016 | Achieved | Report |
MS9 | 1st AIDA-2020 Annual meeting | 1 | M12 | 17/06/2016 | Achieved | Report |
MS10 | Criteria to define, identify, and select key technologies for the PoC Fund | 2 | M12 | 26/05/2016 | Achieved | Report |
MS11 | MPWR submission | 6 | M12 | 03/06/2016 | Achieved | Report |
MS12 | Optical system for the quality assessment of MPGD foil/ mesh mechanical tensioning | 13 | M12 | 26/04/2016 | Achieved | Report |
MS13 | Specification of systems for highly granular scintillator tests | 14 | M12 | 29/04/2016 | Achieved | Report |
MS14 | Assembly and QA chain demonstration for highly granular silicon calorimeters | 14 | M12 | 23/06/2016 | Achieved | Report |
MS15 | Design specifications of test stations for irradiated silicon sensors and LHC oriented frontend electronics | 14 | M12 | 24/06/2016 | Achieved | Report |
MS16 | Specifications for IRRAD sample & user management system and online database fixed | 15 | M12 | 08/06/2016 | Achieved | Report |
MS17 | Design of a transport system for neutron irradiations of large samples | 15 | M12 | 08/06/2016 | Achieved | Report |
Year 2
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS18 | Design document for alignment Toolkit with tight coupling to DD4hep | 3 | M14 | 02/09/2016 | Achieved | Report |
MS19 | Design document for Event Data Model toolkit | 3 | M14 | 02/09/2016 | Achieved | Report |
MS20 | Design document for parallel algorithm scheduling mechanism | 3 | M14 | 02/09/2016 | Achieved | Report |
MS21 | Architectural review of deliverable chips in 65nm run | 4 | M14 | 12/07/2016 | Achieved | Report |
MS22 | Selection of SiGe foundry | 4 | M14 | 12/07/2016 | Achieved | Report |
MS23 | Selection of TSV process | 4 | M14 | 15/07/2016 | Achieved | Report |
MS24 | CFD models available | 9 | M14 | 25/08/2016 | Achieved | Report |
MS25 | Definition of detector interface standards with common DAQ | 5 | M15 | 15/08/2016 | Achieved | Report |
MS26 | First test beam campaign with initial sensor prototype assemblies | 6 | M16 | 21/12/2016 | Achieved | Report |
MS27 | First irradiation campaign with sensor prototype assemblies | 6 | M16 | 21/12/2016 | Achieved | Report |
MS28 | First functional HV/HR-CMOS assembly with capacitive interconnection | 6 | M16 | 30/09/2016 | Achieved | Report |
MS29 | Validation and release of TCAD simulation | 7 | M16 | 02/09/2016 | Achieved | Report |
MS30 | Identification of European company(s) interested in large area sensor production | 2 | M18 | 31/10/2016 | Achieved | Report |
MS31 | Design of cooling systems for tungsten / carbonfibre and for hadron calorimeter structures | 14 | M18 | 31/10/2016 | Achieved | Report |
MS32 | Pixel telescope hardware assembled | 15 | M18 | 31/10/2016 | Achieved | Report |
MS33 | Environmental control system hardware installed | 15 | M18 | 24/10/2016 | Achieved | Report |
MS34 | New Frascati beam line components installed | 15 | M18 | 15/11/2018 | Achieved | Report |
MS35 | Test of various low cost silicon materials for fluence monitor concluded | 15 | M18 | 31/10/2016 | Achieved | Report |
MS36 | Concept of cold box evaluated and design fixed | 15 | M18 | 31/10/2016 | Achieved | Report |
MS37 | Design of the additional cosmic trackers on the other side of the source and on the side walls | 15 | M18 | 01/11/2016 | Achieved | Report |
MS38 | Review and selection of the project(s) to support through the PoC Fund | 2 | M20 | 24/01/2017 | Achieved | Report |
MS39 | Running prototype of USolids using SIMD instructions | 3 | M21 | 30/01/2017 | Achieved | Report |
MS40 | Running prototype for alignment Toolkit | 3 | M21 | 31/01/2017 | Achieved | Report |
MS41 | Running prototype for parallel algorithm scheduling mechanism | 3 | M21 | 31/01/2017 | Achieved | Report |
MS42 | Running prototype for Geant4 based simulation toolkit | 3 | M21 | 30/01/2017 | Achieved | Report |
MS43 | Trigger logic unit (TLU) design ready | 5 | M21 | 06/02/2017 | Achieved | Report |
MS44 | 2nd AIDA-2020 Annual meeting | 1 | M24 | 28/04/2017 | Achieved | Report |
MS45 | 1st AIDA-2020 “Academia meets Industry” event | 2 | M24 | 28/04/2017 | Achieved | Report |
MS46 | EUDAQ interfaces to other DAQs available | 5 | M24 | 23/06/2017 | Achieved | Report |
MS47 | Online event data model available | 5 | M24 | 09/06/2017 | Achieved | Report |
MS48 | Simulation tutorial on HV/HRCMOS TCAD and Geant4 simulations | 6 | M24 | 28/04/2017 | Achieved | Report |
MS49 | Workshop on 3D-planar | 7 | M24 | 27/04/2017 | Achieved | Report |
MS50 | LGAD thickness technological choice | 7 | M24 | 28/04/2017 | Achieved | Report |
MS51 | LGAD Workshop on the characterisation results of the available LGAD sensors | 7 | M24 | 27/04/2017 | Achieved | Report |
MS52 | High-rate RPC prototype ready | 13 | M24 | 30/03/2017 | Achieved | Report |
MS53 | Small-size prototype of the R-WGEM built and qualified | 13 | M24 | 19/04/2017 | Achieved | Report |
MS54 | Integrated FBG sensors for monitoring the mechanical tension of MPGD films and meshes | 13 | M24 | 31/05/2017 | Achieved | Report |
MS55 | Quality control system to ensure the electrical integrity of electrode patterns | 13 | M24 | 26/04/2017 | Achieved | Report |
MS56 | Commissioning of Fibre Test benches | 14 | M24 | 07/04/2017 | Achieved | Report |
MS57 | Design and test of ASICs and readout board prototype for the test infrastructure | 14 | M24 | 19/04/2017 | Achieved | Report |
MS58 | Definition of optical and electrical coupling of readout, interface functionality and DIF design | 14 | M24 | 13/04/2017 | Achieved | Report |
MS59 | Silicon strip reference tracker hardware ready | 15 | M24 | 08/12/2017 | Achieved | Report |
Year 3
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS60 | AIDA-2020 Midterm Review | 1 | M25 | 15/05/2017 | Achieved | Report |
MS61 | Qualification of the new candidate materials for THGEM substrate | 13 | M26 | 16/06/2017 | Achieved | Report |
MS62 | Development of run control ready | 5 | M27 | 31/07/2017 | Achieved | Report |
MS63 | Final design review of 65nm CMOS chips | 4 | M30 | 23/10/2017 | Achieved | Report |
MS64 | Final design review of deliverable chips in SiGe run | 4 | M30 | 18/10/2017 | Achieved | Report |
MS65 | Final design review of deliverable D4.3 | 4 | M30 | 30/10/2017 | Achieved | Report |
MS66 | TLU hardware, firmware and software ready for tests beams | 5 | M30 | 30/11/2017 | Achieved | Report |
MS67 | Data quality monitoring tools ready | 5 | M30 | 06/11/2017 | Achieved | Report |
MS68 | Slow control system ready | 5 | M30 | 18/12/2017 | Achieved | Report |
MS69 | Mechanical structure and supports for large, thin-gap RPCs | 13 | M30 | 30/10/2017 | Achieved | Report |
MS70 | Photon tagging components installed | 15 | M30 | 07/11/2017 | Achieved | Report |
MS71 | Progress review of the selected projects(s) for the PoC Fund | 2 | M34 | 19/02/2018 | Achieved | Report |
MS72 | Bi-annual progress reports and meetings on purification and monitoring | 8 | M35 | 26/03/2018 | Achieved | Report |
MS73 | Bi-annual progress reports and meetings on ionisation charge readout | 8 | M35 | 26/03/2018 | Achieved | Report |
MS74 | Bi-annual progress reports and meetings on light readout | 8 | M35 | 26/03/2018 | Achieved | Report |
MS75 | Bi-annual progress reports and meetings on very high voltage | 8 | M35 | 26/03/2018 | Achieved | Report |
MS76 | Bi-annual progress reports and meetings on magnetisation | 8 | M35 | 26/03/2018 | Achieved | Report |
MS77 | Standard connectors available | 9 | M35 | 18/04/2018 | Achieved | Report |
MS78 | 3rd AIDA-2020 Annual meeting | 1 | M36 | 30/04/2018 | Achieved | Report |
MS79 | 2nd AIDA-2020 “Academia meets Industry” event | 2 | M36 | 30/04/2018 | Achieved | Report |
MS80 | Common DAQ system ready for combined test beams | 5 | M36 | 19/04/2018 | Achieved | Report |
MS81 | Test beam campaign for 3D and planar sensors | 7 | M36 | 30/04/2018 | Achieved | Report |
MS82 | Validated CFD models ready | 9 | M36 | 19/06/2018 | Achieved | Report |
MS83 | Interfacing the FE chip VMM128, GEMROC, TIMEPIX3 to SRS | 13 | M36 | 30/04/2018 | Achieved | Report |
MS84 | Protocol and specifications for MPGD production and quality control | 13 | M36 | 26/06/2018 | Achieved | Report |
MS85 | Installation and commissioning of instantaneous dose rate monitoring system | 15 | M36 | 03/04/2018 | Achieved | Report |
MS86 | Test of the different software modules as event display, camera position tracking and user interface | 15 | M36 | 19/04/2018 | Achieved | Report |
Year 4
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS87 | MPW runs completion | 7 | M42 | 13/03/2019 | Achieved | Report |
MS88 | Integration of USolids extensions for vectorisation in Geant4, ROOT and Geant Vector Prototype | 3 | M44 | 14/12/2018 | Achieved | Report |
MS89 | Application of alignment toolkit to external tracker for PCMAG | 3 | M44 | 21/12/2018 | Achieved | Report |
MS90 | Application of Event Data Model toolkit with high performance I/O to Linear Collider | 3 | M44 | 20/12/2018 | Achieved | Report |
MS91 | Integration of parallel algorithm scheduling mechanism in Gaudi, Marlin and PandoraPFA frameworks | 3 | M44 | 20/04/2020 | Achieved | |
MS92 | Application of advanced Particle Flow algorithms to CMS and LBNE | 3 | M44 | 14/12/2018 | Achieved | Report |
MS93 | RPC performance results with ecofriendly gases and use of recirculation gas systems | 13 | M44 | 01/04/2019 | Achieved | Report |
MS94 | PCB development using HDItechnology and 3D-mounting of chips for MPGD readout | 13 | M44 | 21/02/2019 | Achieved | Report |
MS95 | Test report of deliverable D4.1 | 4 | M46 | 28/02/2019 | Achieved | Report |
MS96 | Test report of deliverable D4.2 | 4 | M46 | 28/02/2019 | Achieved | Report |
MS97 | Test report of deliverable D4.3 | 4 | M46 | 14/04/2020 | Achieved | |
MS98 | Validation radiation damage model with data comparison | 7 | M46 | 19/12/2019 | Achieved | |
MS99 | Advanced Mechanical Distributed facility ready | 9 | M46 | 28/02/2019 | Achieved | Report |
MS101 | 4th AIDA-2020 Annual meeting (Marking the end of the fourth year of the project, Task 1.1) | 1 | M48 | 26/04/2019 | Achieved | Report |
Year 5
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS100 | AIDA-2020 Final meeting | 1 | M60 | 14/05/2020 | Achieved | Report |