Milestones

Year 1 | Year 2 | Year 3 Year 4 | Year 5

Year 1

Mil. no. Milestone name WP no. Planned delivery date Actual delivery date Status Comments
MS1 Consortium Agreement signed 1 M1 05/06/2015 Achieved  
MS2 Project Website launched 2 M1 03/06/2015 Achieved Report
MS3 AIDA-2020 Kick-off meeting 1 M2 22/06/2015 Achieved Report
MS4 Project Communication Plan 2 M2 30/06/2015 Achieved Report
MS5 Network of Technology Transfer Officers established 2 M3 27/07/2015 Achieved Report
MS6 Non-disclosure Agreement and Background declarations ready 2 M3 05/06/2015 Achieved Part of the CA
MS7 Simulation workshop on HV/HR-CMOS TCAD and Geant4 simulations 6 M6 26/05/2016 Achieved

Report

MS8 Advanced Mechanical Distributed facility requirements 9 M9 16/06/2016 Achieved Report
MS9 1st AIDA-2020 Annual meeting 1 M12 17/06/2016 Achieved Report
MS10 Criteria to define, identify, and select key technologies for the PoC Fund 2 M12 26/05/2016 Achieved Report
MS11 MPWR submission 6 M12 03/06/2016 Achieved Report
MS12 Optical system for the quality assessment of MPGD foil/ mesh mechanical tensioning 13 M12 26/04/2016 Achieved Report
MS13 Specification of systems for highly granular scintillator tests 14 M12 29/04/2016 Achieved Report
MS14 Assembly and QA chain demonstration for highly granular silicon calorimeters 14 M12 23/06/2016 Achieved Report
MS15 Design specifications of test stations for irradiated silicon sensors and LHC oriented frontend electronics 14 M12 24/06/2016 Achieved Report
MS16 Specifications for IRRAD sample & user management system and online database fixed 15 M12 08/06/2016 Achieved Report
MS17 Design of a transport system for neutron irradiations of large samples 15 M12 08/06/2016 Achieved Report

Year 2

Mil. no. Milestone name WP no. Planned delivery date Actual delivery date Status Comments
MS18 Design document for alignment Toolkit with tight coupling to DD4hep 3 M14 02/09/2016 Achieved Report
MS19 Design document for Event Data Model toolkit 3 M14 02/09/2016 Achieved Report
MS20 Design document for parallel algorithm scheduling mechanism 3 M14 02/09/2016 Achieved Report
MS21 Architectural review of deliverable chips in 65nm run 4 M14 12/07/2016 Achieved Report
MS22 Selection of SiGe foundry 4 M14 12/07/2016 Achieved Report
MS23 Selection of TSV process 4 M14 15/07/2016 Achieved Report
MS24 CFD models available 9 M14 25/08/2016 Achieved Report
MS25 Definition of detector interface standards with common DAQ 5 M15 15/08/2016 Achieved Report
MS26 First test beam campaign with initial sensor prototype assemblies 6 M16 21/12/2016 Achieved Report
MS27 First irradiation campaign with sensor prototype assemblies 6 M16 21/12/2016 Achieved Report
MS28 First functional HV/HR-CMOS assembly with capacitive interconnection 6 M16 30/09/2016 Achieved Report
MS29 Validation and release of TCAD simulation 7 M16 02/09/2016 Achieved Report
MS30 Identification of European company(s) interested in large area sensor production 2 M18 31/10/2016 Achieved Report 
MS31 Design of cooling systems for tungsten / carbonfibre and for hadron calorimeter structures 14 M18 31/10/2016 Achieved Report
MS32 Pixel telescope hardware assembled 15 M18 31/10/2016 Achieved Report
MS33 Environmental control system hardware installed 15 M18 24/10/2016 Achieved Report
MS34 New Frascati beam line components installed 15 M18 15/11/2018 Achieved Report
MS35 Test of various low cost silicon materials for fluence monitor concluded 15 M18 31/10/2016 Achieved Report
MS36 Concept of cold box evaluated and design fixed 15 M18 31/10/2016 Achieved Report
MS37 Design of the additional cosmic trackers on the other side of the source and on the side walls 15 M18 01/11/2016 Achieved Report
MS38 Review and selection of the project(s) to support through the PoC Fund 2 M20 24/01/2017 Achieved Report
MS39 Running prototype of USolids using SIMD instructions 3 M21 30/01/2017 Achieved Report
MS40 Running prototype for alignment Toolkit 3 M21 31/01/2017 Achieved Report
MS41 Running prototype for parallel algorithm scheduling mechanism 3 M21 31/01/2017 Achieved Report
MS42 Running prototype for Geant4 based simulation toolkit 3 M21 30/01/2017 Achieved Report
MS43 Trigger logic unit (TLU) design ready 5 M21 06/02/2017 Achieved Report
MS44 2nd AIDA-2020 Annual meeting 1 M24 28/04/2017 Achieved Report
MS45 1st AIDA-2020 “Academia meets Industry” event 2 M24 28/04/2017 Achieved Report
MS46 EUDAQ interfaces to other DAQs available 5 M24 23/06/2017 Achieved Report
MS47 Online event data model available 5 M24 09/06/2017 Achieved Report
MS48 Simulation tutorial on HV/HRCMOS TCAD and Geant4 simulations 6 M24 28/04/2017 Achieved Report
MS49 Workshop on 3D-planar 7 M24 27/04/2017 Achieved Report
MS50 LGAD thickness technological choice 7 M24 28/04/2017 Achieved Report
MS51 LGAD Workshop on the characterisation results of the available LGAD sensors 7 M24 27/04/2017 Achieved Report
MS52 High-rate RPC prototype ready 13 M24 30/03/2017 Achieved Report
MS53 Small-size prototype of the R-WGEM built and qualified 13 M24 19/04/2017 Achieved Report
MS54 Integrated FBG sensors for monitoring the mechanical tension of MPGD films and meshes 13 M24 31/05/2017 Achieved Report
MS55 Quality control system to ensure the electrical integrity of electrode patterns 13 M24 26/04/2017 Achieved Report
MS56 Commissioning of Fibre Test benches 14 M24 07/04/2017 Achieved Report
MS57 Design and test of ASICs and readout board prototype for the test infrastructure 14 M24 19/04/2017 Achieved Report
MS58 Definition of optical and electrical coupling of readout, interface functionality and DIF design 14 M24 13/04/2017 Achieved Report
MS59 Silicon strip reference tracker hardware ready 15 M24 08/12/2017 Achieved Report

Year 3

Mil. no. Milestone name WP no. Planned delivery date Actual delivery date Status Comments
MS60 AIDA-2020 Midterm Review 1 M25 15/05/2017 Achieved Report
MS61 Qualification of the new candidate materials for THGEM substrate 13 M26 16/06/2017 Achieved Report
MS62 Development of run control ready 5 M27 31/07/2017 Achieved Report
MS63 Final design review of 65nm CMOS chips 4 M30 23/10/2017 Achieved Report
MS64 Final design review of deliverable chips in SiGe run 4 M30 18/10/2017 Achieved Report
MS65 Final design review of deliverable D4.3 4 M30 30/10/2017 Achieved Report
MS66 TLU hardware, firmware and software ready for tests beams 5 M30 30/11/2017 Achieved Report
MS67 Data quality monitoring tools ready 5 M30 06/11/2017 Achieved Report
MS68 Slow control system ready 5 M30 18/12/2017 Achieved Report
MS69 Mechanical structure and supports for large, thin-gap RPCs 13 M30 30/10/2017 Achieved Report
MS70 Photon tagging components installed 15 M30 07/11/2017 Achieved Report
MS71 Progress review of the selected projects(s) for the PoC Fund 2 M34 19/02/2018 Achieved Report 
MS72 Bi-annual progress reports and meetings on purification and monitoring 8 M35 26/03/2018 Achieved Report
MS73 Bi-annual progress reports and meetings on ionisation charge readout 8 M35 26/03/2018 Achieved Report
MS74 Bi-annual progress reports and meetings on light readout 8 M35 26/03/2018 Achieved Report
MS75 Bi-annual progress reports and meetings on very high voltage 8 M35 26/03/2018 Achieved Report
MS76 Bi-annual progress reports and meetings on magnetisation 8 M35 26/03/2018 Achieved Report
MS77 Standard connectors available 9 M35 18/04/2018 Achieved Report
MS78 3rd AIDA-2020 Annual meeting 1 M36 30/04/2018 Achieved Report 
MS79 2nd AIDA-2020 “Academia meets Industry” event 2 M36 30/04/2018 Achieved Report
MS80 Common DAQ system ready for combined test beams 5 M36 19/04/2018 Achieved Report
MS81 Test beam campaign for 3D and planar sensors 7 M36 30/04/2018 Achieved Report
MS82 Validated CFD models ready 9 M36 19/06/2018 Achieved Report
MS83 Interfacing the FE chip VMM128, GEMROC, TIMEPIX3 to SRS 13 M36 30/04/2018 Achieved Report
MS84 Protocol and specifications for MPGD production and quality control 13 M36 26/06/2018 Achieved Report 
MS85 Installation and commissioning of instantaneous dose rate monitoring system 15 M36 03/04/2018 Achieved Report
MS86 Test of the different software modules as event display, camera position tracking and user interface 15 M36 19/04/2018 Achieved Report

Year 4

Mil. no. Milestone name WP no. Planned delivery date Actual delivery date Status Comments
MS87 MPW runs completion 7 M42 13/03/2019 Achieved Report
MS88 Integration of USolids extensions for vectorisation in Geant4, ROOT and Geant Vector Prototype 3 M44 14/12/2018 Achieved Report 
MS89 Application of alignment toolkit to external tracker for PCMAG 3 M44 21/12/2018 Achieved Report
MS90 Application of Event Data Model toolkit with high performance I/O to Linear Collider 3 M44 20/12/2018 Achieved Report
MS91 Integration of parallel algorithm scheduling mechanism in Gaudi, Marlin and PandoraPFA frameworks 3 M44 20/04/2020 Achieved

Report

Justification for delay

MS92 Application of advanced Particle Flow algorithms to CMS and LBNE 3 M44 14/12/2018 Achieved Report 
MS93 RPC performance results with ecofriendly gases and use of recirculation gas systems 13 M44 01/04/2019 Achieved Report
MS94 PCB development using HDItechnology and 3D-mounting of chips for MPGD readout 13 M44 21/02/2019 Achieved Report
MS95 Test report of deliverable D4.1 4 M46 28/02/2019 Achieved Report
MS96 Test report of deliverable D4.2 4 M46 28/02/2019 Achieved Report
MS97 Test report of deliverable D4.3 4 M46 14/04/2020 Achieved

Report 

Justification for delay

MS98 Validation radiation damage model with data comparison 7 M46 19/12/2019 Achieved

Report

Justification for delay

MS99 Advanced Mechanical Distributed facility ready 9 M46 28/02/2019 Achieved Report
MS101 4th AIDA-2020 Annual meeting (Marking the end of the fourth year of the project, Task 1.1) 1 M48 26/04/2019 Achieved Report 

Year 5

Mil. no. Milestone name WP no. Planned delivery date Actual delivery date Status Comments
MS100 AIDA-2020 Final meeting 1 M60 14/05/2020 Achieved Report